Detail
Challenge
The MoD were experiencing multiple pump and pipe work failures within the
Sea Water fire mains on both the HMS Albion and HMS Bulwark vessels. These
failures were attributed to various causes:
Very high cost of maintenance on pumps
Frequent mechanical seal and motor bearing failures
Inability to meet system design requirements
Various small targeted initiatives to try and improve system performance were
carried out, however it was recognised by the Marine Auxiliary Systems Integrated
Project Team (MXS IPT) that a more joined up systematic, system wide approach was required to address the route cause of the problems.
Solution
Onboard Simulation and Validation
|